Trident Fire Compliance worked with Kyotec Group on their project at Castle Park View in Bristol.

The 26 storey residential tower is the largest building in the Bristol city centre and provided 375 new homes for Bristol residents.

Learn More
Castle Park View | Trident Fire Compliance

Castle Park View

Kyotec Group were responsible for the installation of the external façade of the building.

As part of their works, they were required to install horizontal and vertical cavity barriers to the edge of concrete floor slabs and concrete columns to maintain fire compartmentation as per the building fire strategy.

Kyotec had a robust, well tested, system for the cavity barriers, but they wanted to provide further assurances to their client that the works were completed correctly.

Trident Fire Compliance were employed to carry out a programme of compliance inspections during the build to monitor installations, review records and provide technical guidance on installation guidelines.

Trident attended the project frequently during the build and witnessed varying types of installations.

The standard of installation on the project was excellent by the Kyotec team, but Trident made recommendations on how to accurately record the installations as part of a good operation and maintenance procedure and to comply with Regulation 38.

Each individual“section”of cavity barrier was recorded and referenced. Each installation had an installation detail sheet which outlined the type of installation and the necessary steps to achieve compliance. Each document was completed by the installer, reviewed by the project manager, and subsequently reviewed by Trident to ensure accuracy.

At the end of the project, the works were completed in accordance with tested design and there were comprehensive records of the installations completed in the building.

Trident provided a final report on the overall completion of the works and confirmed compliance to specification.

 

Proudly trusted by...

Related Case Studies

Contact Us

Talk to us about your next project

Trident Fire Compliance strive to be the first port of call with regards to passive fire protection and fire safety. We want you to get it right first time.

Our expert consultants can work with you through design, construction and end-use of a building to ensure it is compliant to the regulations and guidelines.

Get in touch to see how we can help you. Let’s work together to achieve compliance.


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply. By submitting this form you agree to our privacy policy.